Modernization of the Berdavan Village Reservoir and Irrigation System in Tavush Region

icon

Modernization of the Berdavan Village Reservoir and Irrigation System in Tavush Region Funded by: The H. Hovnanian Family Foundation

Core Values Image

2022 – Modernization of the Berdavan Village Reservoir and Irrigation System in Tavush Region Funded by: The H. Hovnanian Family Foundation

Under this contract, the irrigation system built during the Soviet era—consisting of a reservoir, pump stations, and water pipelines—was planned for modernization.

Key Findings and Challenges:

Detailed field studies revealed that the irrigation system relied on two nearby pump stations. One received water by gravity from a 3,000 m³ reservoir, and the other sourced water from a deep well. However, due to climate change, underground water levels have dropped by nearly 40%, leading to reduced water levels in both the reservoir and the well.

As a result:

  • The reservoir experienced sediment accumulation, reducing its volume by around 1,000 m³.
  • The dam's upper slope structures deteriorated, with partial surface erosion.
  • Poor system operation caused excess water to flow into Azerbaijan, without being used efficiently by the community.

Main Design and Rehabilitation Works:

1. Reservoir Reconstruction with an Earthen Dam

  • Stability checks and modeling were performed based on real flow conditions.
  • Anti-filtration measures, slope reinforcements, sediment removal, and dam surface restoration were included.
  • A new intake structure was designed 50 meters upstream to draw water 1.5 meters higher than the existing level, enabling a design flow of 150 L/s.
  • Water will be transported from the new intake to the reservoir through a 1.5m-deep earthen channel, designed per SNiP 2.06.03-85 standards.
  • A geomembrane will protect the upper slope and dam crest from wave action, filtration, vegetation roots, and weathering.

2. Construction of Pump Station Sump and Supply Channel

  • Demolition of the old sump and deepening of the floor by 1 meter.
  • Construction of a new 45 m³ reinforced concrete sump.
  • New inlet and outlet gates, and a 2.2m-wide concrete supply channel.
  • Installation of reinforced control gates at the channel's entrance.

3. Renovation of Pump Station and Guardhouse Buildings

  • Capital repairs included:
    • Roof reconstruction
    • Façade and window/door replacements
    • Metal gate installation
    • Construction of a canopy at the entrance
    • Installation of two 2-ton electric hoists on extended monorails
    • Concrete floor repair and interior finishes

4. Pumps and Pipe Fittings

  • Two 130m head, 150 m³/h capacity pumps were installed for flexible and efficient operation.
  • Old and new pump units will work autonomously, each serving specific irrigation lines.
  • A check valve ensures safe operation when old and new systems run concurrently.
  • Complete replacement of outdated pipelines and fittings with new, durable materials.

5. Electrical System Modernization

  • The existing 560 kW oil transformer is operational, but outdated control panels were unsafe.
  • Replaced with modern, reliable switchboards and protection devices.
  • All power cables and conductors were fully replaced due to degradation.
  • The lighting network was also fully upgraded.

6. Construction of Irrigation Pipelines

  • Existing system included pressure lines from both pump stations, delivering water to high-elevation distribution chambers at 692m and 706m.
  • Due to water scarcity, the first pump station was proposed to be decommissioned, and the second station used instead.
  • A new underground polyethylene pipeline was built to connect the second station with the first station's original delivery line.
  • New polyethylene pipelines with adequate hydrants replaced the older distribution lines.
  • Topography, roadways, and utility infrastructure were considered in the layout.

Expected Results:

  • ~45 hectares of land previously left unirrigated due to water shortages will now be irrigated efficiently.
  • The interconnection of the two pump stations will ensure balanced water distribution and support overall system demand.
  • Annual income from newly irrigated land is expected to exceed 125 million AMD starting from year 3–5.
  • Reservoir volume increased from 4,000 m³ to 12,000 m³.
DETAILS
Funding Institution
THE H. HOVNANIAN FAMILY FOUNDATION
Client
Berdavan community
Country
Armenia
Date
2022
Service
Modernization of the Berdavan Village Reservoir and Irrigation System